What is the status of system requirements after they have undergone the confirmation process?

Prepare for the ASEP INCOSE Systems Engineering Test. Enhance your knowledge with dynamic flashcards and detailed multiple-choice questions. Get hints and explanations on every question for comprehensive understanding. Ace your exam with confidence!

After the confirmation process, system requirements are deemed verified. Verification is the process of ensuring that the requirements have been met as specified. This means that the development and engineering processes have been executed correctly to fulfill the stated needs in the requirements. Verification typically involves checking against the criteria set forth during the requirements definition phase to confirm that the proper outputs are delivered based on the requirements specified.

When requirements are verified, it indicates that the development team has not only built the system but has also confirmed that it operates as intended per the documented requirements. This process is crucial because it establishes that the requirements can be traced back to stakeholders' needs and ensures that the end product aligns with the initial expectations.

In contrast, the notion of being validated refers to a different aspect where the focus is on whether the right product has been built to meet the user's needs. The status of being finalized might suggest that the requirements have been accepted but does not convey that they have been confirmed through the verification process. Being documented implies that the requirements are recorded and can be referenced, but it does not speak to their verification status. Thus, verification is the correct term to describe the requirements' status post-confirmation.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy